We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.Â
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.Â
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Laurel School's Gator Garage Renovation
September 10, 2025Mission
The °µÍø½ûÇø Foundation Distributes $60K in its Sixth Grant Cycle
September 8, 2025Mission
Congratulations Carter Daly Recipient of Harry F. Gaeke Memorial Scholarship
September 4, 2025News
BILA Solar North American Headquarters is a Monumental Awards Finalist
September 2, 2025Awards
2025 Construction Employers Association Building Excellence & Craftsmanship Awards
August 27, 2025Awards
Completion of Kershaw Water Treatment Plant
August 26, 2025News
Fourth Annual °µÍø½ûÇø Foundation Invitational - Cleveland
August 25, 2025Mission
Summer 2025 Co-Op Semester in Review
August 22, 2025News
2025 Builders Exchange of Dayton Awards
August 21, 2025Awards
West Carrollton Elementary School Ribbon Cutting
August 20, 2025News
°µÍø½ûÇø Named to the 2025 OSBA Business Honor Roll
August 19, 2025Awards
Chris Shafer Recognized as CFO of the Year
August 18, 2025Awards