April 21, 2025 News
We're excited to share the progress on NEORSD's Westerly Chemically Enhanced High-Rate Treatment (CEHRT) project. To date, we've finished 20,500 cubic yards of concrete! Check out some of the recent updates on each segment of the project below.Â
💧 New High-Rate Disinfection (HRD) Tank: All concrete associated with the new HRD Tank has been completed and the installation of process equipment located in the tank has begun.
💧 Control Building: Roofing and exterior insulated metal wall panels have been completed and the process equipment installation within the building is ongoing.Â
💧 Existing Combined Storm Overflow Treatment Facility (CSOTF): Process equipment installation is wrapping up within these tanks.
Volunteering at St. Vincent de Paul - Dayton, OH
June 2, 2023Mission
Take a Sneak Peek inside Dayton Metro Library's newest branch
May 31, 2023News
John Cleveland Wins 2023 °µÍø½ûÇø Core Value Award
May 30, 2023News
Dayton Business Journal Top 100 Companies
May 26, 2023Awards
25 °µÍø½ûÇø Employees Volunteer with Habitat for Humanity of Greater Dayton
May 24, 2023Mission
One °µÍø½ûÇø, One Mission Food Drive
May 19, 2023Mission
Stand Down for Safety
May 18, 2023News
Teaching Preble County 4th Graders about Construction
May 17, 2023Mission
°µÍø½ûÇø Construction: Solidly Built on Century of Success
May 16, 2023News
°µÍø½ûÇø's Indianapolis Office Wins CCS Safety Achievement Award
May 12, 2023Awards
New Kenton Ridge PK-12 facility approaching completion
May 11, 2023News
°µÍø½ûÇø's Kenny Bowshier Receives CCS Outstanding Craftsperson Award
May 9, 2023Awards